Front of the under construction Estancia Theater
flier annoucing updates to the Estancia Theater Project

In Progress:

  • Exterior concrete panel installation
     
  • Window installation
     
  • Roof installation
     
  • Hardscape installation
     
  • Decorative wood fiber panels installation
     
  • Finalizing furniture and theater lighting selection

Recently Completed:

  • Firewater connection on Placentia Avenue
     
  • Exterior plaster application
     
  • Blackbox theatrical rigging
     
  • Building connected to power

Construction completion anticipated by the start of the 2025-26 school year