Estancia Theater Project Update
March 2025
In Progress:
- The first layer of exterior plaster is being applied to parts of the building.
- The roofing for the theater and black box areas is almost finished.
- Grading inside the theater is nearly complete.
- The installation of structural steel for the overhead acoustic panels is almost done.
- Interior walls and ceiling framing are continuing throughout the project.
- Concrete planter walls have been poured.
Construction completion anticipated by the start of the 2025/26 school year