  • Roof Construction: Concrete roof deck has been poured at all levels.
     
  • Site Work: New curb and gutter poured throughout project boundaries.
     
  • Wall Framing: Exterior and interior wall framing in progress.
     
  • Plumbing, Electrical Installation: Plumbing, electrical, and mechanical systems continue to be installed.

Construction completion anticipaed by the start of the 2025/26 school year.